Kilbourn Reservoir Park Project Update January 16, 2007

Kilbourn Reservoir Park Project Update
Dec. 8, 2006 - Jan. 16, 2007


(scroll down for project photos)

Removal of the internal structure of the Kilbourn Reservoir is nearly complete. A wrecking crew continues to demolish the concrete cap and the interior walls of the reservoir. The concrete cap and columns are approximately 90% demolished. There remains a large volume of concrete to be crushed and stripped of metal and rebar. The areas of the excavation were backfilled with the existing soil that had been removed. The concrete from the excavation will be used in the reservoir as backfill. Work will soon begin on grading in the area west of the reservoir access path and east of the baseball diamond area and the construction access road. During business hours, please direct any questions or concerns to: Mr. Tony Supinski, Water Works Engineering asupin@mpw.net or (414) 286-3826. These updates are available on the Milwaukee Water Works website, www.water.mpw.net. At the home page, click on the graphic depicting the Kilbourn Reservoir Park Project.


Existing asphalt path on the upper west edge of reservoir is removed.(Dec. 8, 2006)



Construction equipment access trail and excavation of north face (Dec. 8, 2006)



North wall of reservoir exposed. (Dec. 8, 2006)



Demolishing the concrete cap and east interior wall of the reservoir (Jan. 5, 2007)



Crushing concrete (Jan. 5, 2007)



4.x4. drainage cuts inside reservoir (Jan. 5, 2007)



Removing the upper concrete edges along the northeast section of the reservoir (Jan. 9, 2007)



A view inside the reservoir (Jan. 10, 2007)



Crushing concrete (Jan. 9, 2007)



Removing organic debris from the site (Jan. 9, 2007)



A view of the reservoir looking south (Jan. 10, 2007)



Demolishing the concrete cap and crushing concrete. (Jan. 11, 2007)



The northern and eastern interior of the reservoir has been stripped of concrete. (Jan. 11, 2007)



Crushing concrete (Jan. 12,2007)



Remaining section of concrete cap. (Jan. 12, 2007)



Demolishing the west interior wall, concrete cap and columns (Jan. 16, 2007)



Removing rebar and metal from crushed concrete (Jan. 16, 2007)



Demolishing the west interior wall, concrete cap and columns (Jan. 16, 2007)



Demolishing the west interior wall, concrete cap and columns (Jan. 16, 2007)


The Milwaukee Water Works will continue to provide updates as developments occur. Check our web site regularly: http://www.water.mpw.net/1specialprojects.htm