Kilbourn Reservoir Park Project Update January 25, 2007
Kilbourn Reservoir Park Project Update
Jan. 17, 2007 - Jan. 25, 2007
A crew continues to demolish the western interior wall, interior support columns, and the concrete cap of the
reservoir. The concrete is then stripped of metal and rebar and will be reused as backfill, along with soil that had
been removed prior to demolition. The southwestern interior wall remains.
During business hours, please direct any questions or concerns to: Mr. Tony Supinski, Water Works Engineering
mailto:asupin@mpw.net or (414) 286-3826.
These updates are available on the Milwaukee Water Works website, www.water.mpw.net. At the home page, click on the
graphic depicting the Kilbourn Reservoir Park Project.
Demolishing the west interior wall, concrete cap and columns (Jan. 17, 2007)
Demolishing the west interior wall, concrete cap and columns (Jan. 17, 2007)
Reworking the crushed concrete to remove metal and rebar material (Jan. 17, 2007)
Demolishing the west interior wall (Jan. 17, 2007)
The remaining section of the concrete cap and columns to be demolished (Jan. 17, 2007)
The Milwaukee Water Works will continue to provide updates as developments occur. Check our web site regularly: