Apr 17, 2007  |  Feb 19, 2007  |  Jan 25, 2007  |  Jan 16, 2007  |  Oct 27, 2006 
Oct 20, 2006  |  Apr 2006  |  Jan 2006  |  Oct 2005  |  Jan 2005  |  Jan 2002  |  May 2000

Milwaukee Water Works Home


Kilbourn Reservoir Park Project Update February 19, 2007

Kilbourn Reservoir Park Project Update
Jan 26, 2007 - Feb. 16, 2007


(scroll down for project photos)

1/30/07 - Crews were about 50% finished with crushing the concrete and removing metal and rebar from the demolished sections of the reservoir. They also were removing and crushing the upper concrete edges along the west rim of the reservoir. All of the interior walls have been stripped of concrete. The demolished concrete is being used as backfill and the rebar and metal are being moved from the site for disposal. The upper concrete edges remain along the southwestern and western rim of the reservoir. Some of the tree protection and erosion control around the site will be repaired.

During business hours, please direct any questions or concerns to: Mr. Tony Supinski, Water Works Engineering asupin@mpw.net or (414) 286-3826.


Removing and crushing the upper concrete edges along the west rim of the reservoir.
(Jan. 30, 2007)



Removing and crushing the upper concrete edges along the west rim of the reservoir Piles of rebar and metal from the demolition of the concrete cap and reservoir are being staged in loads to be hauled off of the site.
(Jan. 30, 2007)



Crushing the upper concrete edges along the west rim of the reservoir.
(Jan. 30, 2007)



Extending the interior reservoir access road.
(Jan. 30, 2007)



View of eastern slope looking west from W. North Ave. showing the area where the stairway was removed
(Feb. 19, 2007)



View of western slope looking east from W. North Ave. showing the area where the stairway was removed
(Feb. 19, 2007)


The Milwaukee Water Works will continue to provide updates as developments occur. Check our web site regularly: http://www.water.mpw.net/1specialprojects.htm